久久久久久久久久免免费精品_国产免费午夜a无码v视频_男女免费观看在线爽爽爽视频_亚洲国产欧美日本视频_国产欧美精品一区二区色综合____

您好!歡迎訪問消防設(shè)備安裝廠家-氣體滅火設(shè)備價(jià)格-七氟丙烷滅火系統(tǒng)-七氟丙烷安裝價(jià)格-杭州金鷹消防!
專業(yè)氣體消防設(shè)備智能消防解決方案專業(yè)供應(yīng)商打造中國(guó)專業(yè)的氣體消防設(shè)備供應(yīng)商
全國(guó)統(tǒng)一服務(wù)熱線13777882119
聯(lián)系我們

消防設(shè)備安裝廠家-氣體滅火設(shè)備價(jià)格-七氟丙烷滅火系統(tǒng)-七氟丙烷安裝價(jià)格-杭州金鷹消防
電話:13777882119
傳真:0571-88212867
地址:杭州市錢塘區(qū)河莊工業(yè)區(qū)
當(dāng)前位置 : 首頁 > 業(yè)內(nèi)新聞

杭州消防工程設(shè)計(jì)審核辦理的具體步驟

發(fā)表時(shí)間 : 2020-07-03 * 瀏覽 : 5693

  消防設(shè)計(jì)審核是早期匹配過程中一個(gè)復(fù)雜、困難、長(zhǎng)期的過程。由于消防隊(duì)與建設(shè)項(xiàng)目用地規(guī)劃部門屬于平行部門,有些手續(xù)可以并行辦理。對(duì)早期匹配工程師的建議是盡早與消防隊(duì)溝通,并在條件允許的情況下提前檢查圖紙。為了避免不均勻的工序和無法開始施工。


  《中華人民共和國(guó)消防法》第十一條:大型人員密集場(chǎng)所和國(guó)務(wù)院公安部門規(guī)定的其他特種建設(shè)項(xiàng)目,建設(shè)單位應(yīng)當(dāng)向公安機(jī)關(guān)消防機(jī)構(gòu)報(bào)送消防設(shè)計(jì)文件。供審核。

  《中華人民共和國(guó)消防法》第十二條:依法應(yīng)當(dāng)經(jīng)公安機(jī)關(guān)消防機(jī)構(gòu)審核的建筑工程,由審批該建筑工程施工許可證的部門不得發(fā)給施工許可證,并不得施工。建筑施工單位和施工單位不得施工;已經(jīng)取得施工許可證的其他建筑工程,應(yīng)當(dāng)依法進(jìn)行抽查。未竣工的,停止施工。

  以上兩條引自《中華人民共和國(guó)消防法》。消防設(shè)計(jì)審核主要針對(duì)建筑、給排水、電氣等專業(yè)。然而,在沒有消防設(shè)計(jì)審核的情況下,樁基工程是不允許建造的。否則,將對(duì)施工單位和施工單位處以罰款。

  在這里,消防設(shè)計(jì)審核是針對(duì)建筑施工項(xiàng)目,根據(jù)我自己的經(jīng)驗(yàn),可以分為空白類型、精裝類型兩種類型,這意味著當(dāng)干燥的空白房間需要為消防設(shè)計(jì)審核申報(bào)時(shí),當(dāng)完成空白房間時(shí),還需要申報(bào)消防設(shè)計(jì)審核以進(jìn)行精細(xì)裝修。(有平方米限制,低于300_或投資)。不需要處理30萬人以下的人員,但如果人員擁擠的地方,不需要處理,直到200人以下)。驗(yàn)收過程中,未進(jìn)行消防設(shè)計(jì)審核和申報(bào)工作的,不予驗(yàn)收。向當(dāng)?shù)叵狸?duì)申報(bào)已完成土建消防設(shè)計(jì)審核和精裝消防設(shè)計(jì)審核后,可進(jìn)行逐級(jí)驗(yàn)收(先土建后精裝)和土建精裝的統(tǒng)一驗(yàn)收。(俗稱兩報(bào)一考)

  認(rèn)真地說,下面是如何進(jìn)行消防設(shè)計(jì)審核的簡(jiǎn)要說明:

  1、處理的前提條件:

  2、取得建設(shè)工程規(guī)劃許可證。

  3、獲得地圖檢查證書。

  4、獲得消防通知。

  5、完成建筑、結(jié)構(gòu)、管道和電氣圖紙和文件的設(shè)計(jì)。(裝飾裝修圖設(shè)計(jì))

  6、加工要求:

  7、《建筑工程消防設(shè)計(jì)審核申報(bào)表》(以下簡(jiǎn)稱:消防隊(duì)以下5000,消防隊(duì)以上5000,特別是重大工程需要消防隊(duì)處理)、《小型工程消防設(shè)計(jì)審核記錄表》、《大型工程消防設(shè)計(jì)審核表》形式

  很明顯,注意力的程度是不同的…注:記錄表是直接辦理竣工圖的提供,以取得記錄證書,但設(shè)計(jì)審核表需要完善資料,報(bào)當(dāng)?shù)叵狸?duì)報(bào)建,竣工圖審核合格后,可在設(shè)計(jì)奧迪完成后出具圖紙審核。T證書…

  8、兩份營(yíng)業(yè)執(zhí)照和組織機(jī)構(gòu)代碼證。(蓋建設(shè)單位章)

  9、法人身份證、授權(quán)委托書、受托人身份證。(蓋建設(shè)單位章)

  10、建筑工程規(guī)劃許可證(精裝修消防設(shè)計(jì)審核還需提供民用消防設(shè)計(jì)審核證書)

  11、設(shè)計(jì)單位和圖紙審查單位的組織機(jī)構(gòu)代碼證、營(yíng)業(yè)執(zhí)照,設(shè)計(jì)單位和圖紙審查人員的單位資格證(分別加蓋設(shè)計(jì)單位、圖紙審查機(jī)構(gòu)和施工單位公章)單位)各兩份。

  12、完整的專業(yè)圖紙

  13、外部熱輸入設(shè)計(jì)實(shí)踐


Fire design audit is a complex, difficult and long-term process in the early matching process. Because the fire brigade and the land planning department of construction projects belong to parallel departments, some procedures can be handled concurrently. The suggestion for early matching engineers is to communicate with the fire brigade as soon as possible and check the drawings in advance if conditions permit. In order to avoid uneven work procedures and inability to start construction.

Article 11 of the Fire Protection Law of the People's Republic of China: For large-scale personnel-intensive places and other special construction projects stipulated by the public security department under the State Council, the construction unit shall submit fire protection design documents to the fire control institutions of public security organs. For review.

Article 12 of the Fire Protection Law of the People's Republic of China: Construction projects that should be examined and verified by fire control agencies of public security organs according to law shall not be granted construction permits or constructed by the departments that examine and approve the construction permits of such construction projects. Construction units and construction units shall not construct; other construction projects that have obtained construction permits shall be subject to spot checks according to law. If the project is not completed, the construction shall be stopped.

The above two are quoted from the Fire Protection Law of the People's Republic of China. Fire design audit is mainly aimed at building, water supply and drainage, electrical and other specialties. However, in the absence of fire design audits, pile foundation engineering is not allowed to be constructed. Otherwise, the construction unit and the construction unit will be fined.

Here, fire design audit is for building construction projects. According to my own experience, it can be divided into two types: blank type and hardcover type. This means that when dry blank room needs to be declared for fire design audit, when the blank room is completed, it also needs to declare fire design audit for fine decoration. 。 (There is a square metre limit, less than 300 or investment). There is no need to deal with people under 300,000, but if there are crowded places, there is no need to deal with them until 200 people or less. In the process of acceptance, those who fail to check and declare fire control design shall not be accepted. After declaring to the local fire brigade that the civil fire protection design audit and the hardcover fire protection design audit have been completed, the step-by-step acceptance (first civil construction and then hardcover) and the unified acceptance of the civil hardcover can be carried out. (commonly known as two newspapers and one examination)

Seriously speaking, the following is a brief description of how to conduct fire design audits:

1. Prerequisites for processing:

2. Obtain construction project planning license.

3. Obtain the map inspection certificate.

4. Get fire control notice.

5. Complete the design of building, structure, pipeline and electrical drawings and documents. (Decoration design)

6. Processing requirements:

7. Fire Design Audit Declaration Form for Construction Engineering (hereinafter referred to as: Fire Brigade below 5000, Fire Brigade above 5000, especially major projects need fire brigade processing), "Fire Design Audit Record Form for Small-scale Engineering" and "Fire Design Audit Form for Large-scale Engineering" forms

Obviously, the degree of attention varies. Note: Record sheet is to provide the completed drawings directly to obtain the record certificate, but the design audit sheet needs to improve the information and report to the local fire brigade for construction. When the completed drawings are qualified, the drawings can be issued after the completion of the design auditing by Audi. T certificate...

8. Two business licenses and organization code certificates. (Stamp of Construction Unit)

9. Legal person identity card, power of attorney and trustee identity card. (Stamp of Construction Unit)

10. Construction Engineering Planning License (Civil Fire Design Audit Certificate is also required for fire design audit of fine decoration)

11. Two copies of the organization code certificate, business license of the design unit and the drawing examination unit, and the unit qualification certificate of the design unit and the drawing examination personnel (with the official seal of the design unit, the drawing examination organization and the construction unit respectively).

12. Complete professional drawings

13. Design Practice of External Heat Input